" Officer grants a further period of time before the date of final payment under the contract), notifies the Contracting Officer in writing of the causes of delay. The Contracting Officer shall ascertain the facts and the extent of the delay and extend... "
Code of Federal Regulations: Containing a Codification of Documents of ... - Stranica 198
1972
Potpun prikaz - O ovoj knjizi

Cases Decided in the Court of Claims of the United States, Opseg 111

United States. Court of Claims - 1948 - Broj stranica: 886
...beginning of any such delay, or such longer period as may be allowed by the Contracting Officer, notify the Contracting Officer in writing of the causes of...judgment the findings of fact justify such an extension. The decision of the Contracting Officer thereon shall be final, subject only to appeal under Article...
Potpun prikaz - O ovoj knjizi

Cases Decided in the United States Court of Claims ... with ..., Opseg 115

United States. Court of Claims, Audrey Bernhardt - 1950 - Broj stranica: 940
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30 days,...
Potpun prikaz - O ovoj knjizi

Cases Decided in the Court of Claims of the United States, Opseg 94

United States. Court of Claims - 1942 - Broj stranica: 818
...the beginning of any such delay notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...fact justify such an extension, and his findings of facts thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30...
Potpun prikaz - O ovoj knjizi

Cases Decided in the Court of Claims of the United States, Opseg 105

United States. Court of Claims - 1946 - Broj stranica: 920
...liquidated damages because of unforeseeable causes of delay, including strikes, and it provides that the contracting officer "shall ascertain the facts...judgment the findings of fact justify such an extension." This, of course, makes it mandatory upon the contracting officer to make findings of fact upon an application...
Potpun prikaz - O ovoj knjizi

Cases Decided in the Court of Claims of the United States, Opseg 107

United States. Court of Claims - 1947 - Broj stranica: 806
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...of fact justify such an extension, and his findings pi fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within...
Potpun prikaz - O ovoj knjizi

Cases Decided in the Court of Claims of the United States, Opseg 104

United States. Court of Claims - 1946 - Broj stranica: 936
...contract) notify the contracting officer in writing of the causes 01 delay, who shall ascertain the fact and the extent of the delay and extend the time for...justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30 days,...
Potpun prikaz - O ovoj knjizi

Decisions of the Comptroller General of the United States, Opseg 29

United States. General Accounting Office - 1950 - Broj stranica: 710
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30 days,...
Potpun prikaz - O ovoj knjizi

The Code of Federal Regulations of the United States of America ..., Knj.2

1939 - Broj stranica: 1306
...final settlement of the contract) notify the contracting officer In writing of the causes of delay, who shall ascertain the facts and the extent of the delay...Justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal within 30 days,...
Potpun prikaz - O ovoj knjizi

Code of Federal Regulations: Containing a Codification of Documents of ...

1982 - Broj stranica: 690
...restrictions, strikes, freight embargoes, unusually severe weather, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control...as provided in the clause of this contract entitled "Disputes." ' (e) If, after notice of termination of the Contractor's right to proceed under the provisions...
Potpun prikaz - O ovoj knjizi

Code of Federal Regulations: Containing a Codification of Documents of ...

1968 - Broj stranica: 1348
...weather, or delays of subcontractors or suppliers arising from unforseeable causes beyond the control and without the fault or negligence of both the Contractor...as provided In the clause of this contract entitled "Disputes." ' (e) If, after notice of termination of the Contractor's right to proceed under the provisions...