...The contract shall be amended accordingly, and the Contractor shall be paid the agreed amount. (e) In the event of the failure of the Contractor and the...previously paid to the Contractor for the performance of this contract prior to the effective date of the Notice of Termination, and such of these costs as... | |
| 1979 - Broj stranica: 1078
...The contract shall be amended accordingly, and the Contractor shall be paid the agreed amount. (e) In the event of the failure of the Contractor and the...as follows: (1) If the settlement includes cost and feeCD There shall be included therein all costs and expenses reimbursable in accordance with this contract,... | |
| 1978 - Broj stranica: 1058
...The contract shall be amended accordingly, and the Contractor shall be paid the agreed amount. (e) In the event of the failure of the Contractor and the...as follows: (1) If the settlement includes cost and fee(i) There shall be included therein all costs and expenses reimbursable in accordance with this... | |
| 1982 - Broj stranica: 690
...The contract shall be amended accordingly, and the Contractor shall be paid the agreed amount. (e) In the event of the failure of the Contractor and the...to the Contractor the amount determined as follows: (I) If the settlement includes cost and fee— (i) There shall be included therein all costs and expenses... | |
| 1974 - Broj stranica: 788
...provided In paragraph (d), as to the amounts with respect to costs and fee, or as to the amount of th* fee? to be paid to the Contractor In connection with...previously paid to the Contractor for the performance of thle contract prior to the effective date of th« Notice of Termination, and such of these costs as... | |
| 1969 - Broj stranica: 790
...to agree in whole or in part, as provided in paragraph (d) , as to the amounts with respect to costs to be paid to the Contractor in connection with the...to the Contractor the amount determined as follows: (I) There shall be Included therein all costs and expenses reimbursable in accordance with this contract,... | |
| 1971 - Broj stranica: 850
...to agree in whole or In part, as provided In paragraph (d) , as to the amounts with respect to costs to be paid to the Contractor in connection with the...to the Contractor the amount determined as follows: (i) There shall be included therein all costs and expenses reimbursable in accordance with this contract,... | |
| 1972 - Broj stranica: 914
...subject to any review required by the contractIng agency's procedure In effect as of the § 7-16.958 date of execution of this contract, determine, on...previously paid to the Contractor for the performance of this contract prior to the effective date of the Notice of Termination, and such of these costs as... | |
| 1977 - Broj stranica: 1240
...agree as provided in paragraph (d) upon the whole amount to be paid to the Contractor by reason of the termination of work pursuant to this clause, the...the termination and shall pay to the Contractor the amounts determined as follows: (1) For completed supplies accepted by the Government (or sold or acquired... | |
| 1969 - Broj stranica: 628
...as provided in paragraph (d) upon the whole amount to be paid to the Contractor by reason of lîie termination of work pursuant to this clause, the Contracting...the termination and shall pay to the Contractor the amounts determined as follows: ( 1 ) With respect to all contract work performed prior to the effective... | |
| |