" Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change: Provided, however, That the Contracting Officer, if he decides that the facts justify... "
Code of Federal Regulations: Containing a Codification of Documents of ... - Stranica 337
1972
Potpun prikaz - O ovoj knjizi

Cases Decided in the United States Court of Claims ... with ..., Opseg 154

United States. Court of Claims, Audrey Bernhardt - 1968 - Broj stranica: 922
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the...receive and act upon any such claim asserted at any time/prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute...
Potpun prikaz - O ovoj knjizi

Code of Federal Regulations: Containing a Codification of Documents of ...

1982 - Broj stranica: 712
...or not changed by any such order, an equitable adjustment shall be made (i) in the estimated cost or delivery schedule, or both, (ii) in the amount of...to any adjustment shall be a dispute concerning a question of fact within the meaning of 7.403-61 CFR TITLE 41 CHAPTER 18 CLAUSES FOR COST-TYPE R6D CONTRACTS...
Potpun prikaz - O ovoj knjizi

The Code of Federal Regulations of the United States of America

1972 - Broj stranica: 914
...cost or delivery schedule, or both, (2) In the amount of any fee to be paid to the Contractor, and (3) In such other provisions of the contract as may be...to any adjustment shall be a dispute concerning a question of fact within the meaning of the clause of thla contract entitled "Disputes". However, nothing...
Potpun prikaz - O ovoj knjizi

Code of Federal Regulations: Containing a Codification of Documents of ...

1969 - Broj stranica: 790
...cost or delivery schedule, or both, (2) in the amount of any fee to be paid to the Contractor, and (3) in such other provisions of the contract as may be...to any adjustment shall be a dispute concerning a question oí fact within the meaning of the clause oí this contract entitled "Disputes". However,...
Potpun prikaz - O ovoj knjizi

Code of Federal Regulations: Containing a Codification of Documents of ...

1972 - Broj stranica: 914
...cost or delivery schedule, or both, (2) in the amount of any fee to be paid to the Contractor, and (3) in such other provisions of the contract as may be...contract. Failure to agree to any adjustment shall bea dispute concerning a question of fact within the meaning of the clause of this contract entitled...
Potpun prikaz - O ovoj knjizi

Code of Federal Regulations: Containing a Codification of Documents of ...

1971 - Broj stranica: 850
...cost or delivery schedule, or both, (2) In the amount of any fee to be paid to the Contractor, and (3) in such other provisions of the contract as may be...asserted at any time prior to final payment under thla contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact...
Potpun prikaz - O ovoj knjizi

The Code of Federal Regulations of the United States of America

1975 - Broj stranica: 172
...order, an equitable adjustment shall be made (1) In the price or delivery schedule, or both and (2) in such other provisions of the contract as may be...receive and act upon any such claim asserted at any tune prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute...
Potpun prikaz - O ovoj knjizi

The Code of Federal Regulations of the United States of America

1975 - Broj stranica: 1236
...claims by the Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor of the...to any adjustment shall be a dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract However, nothing in this...
Potpun prikaz - O ovoj knjizi

Code of Federal Regulations: Containing a Codification of Documents of ...

1967 - Broj stranica: 2356
...Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor of the...to any adjustment shall be a dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract. However, nothing hi...
Potpun prikaz - O ovoj knjizi

Code of Federal Regulations: Containing a Codification of Documents of ...

1964 - Broj stranica: 676
...equitable adjustment shall be made in the contract price or the time of performance, or both, and the contract shall be modified In writing accordingly....Justify such action, may receive and act upon any claim asserted at any time prior to final payment under this contract. Where the cost of property made...
Potpun prikaz - O ovoj knjizi