| United States. Court of Claims, Audrey Bernhardt - 1963 - Broj stranica: 938
...due to the Contractor by reason of the termination. (d) Subject to the provisions of paragraph (c), the Contractor and the Contracting Officer may agree...partial termination of work pursuant to this clause, which amount or amounts may include a reasonable allowance for profit, but only on work done in connection... | |
| United States. Court of Claims, Audrey Bernhardt - 1955 - Broj stranica: 908
...in the possession of the Contractor and in which the Government has or may acquire an interest. (c) The Contractor and the contracting officer may agree...total or partial termination of work pursuant to this Section, which amount or amounts may include a reasonable allowance for profit, and the Government... | |
| 1939 - Broj stranica: 1306
...in the possession of the contractor and In which the Government has or may acquire an Interest. (c) The contractor and the contracting officer may agree...total or partial termination of work pursuant to this Article, which amount or amounts may Include a reasonable allowance for profit, and the Government... | |
| United States. Office of War Mobilization - 1944 - Broj stranica: 128
...in the possession of the contractor and in which the Government has or may acquire an interest. (c) The contractor and the contracting officer may agree...total or partial termination of work pursuant to this article, which amount or amounts may include a reasonable allowance for profit, and the Government... | |
| United States. War Department - 1944 - Broj stranica: 72
...Settlement. The uniform Termination Article for Fixed Price Supply Contracts (PR 15-901) provides that the contractor and the contracting officer may agree...contractor by reason of the total or partial termination of the work." It is also provided that in the event a negotiated settlement cannot be agreed upon, for... | |
| 1974 - Broj stranica: 1020
...subject to any Settlement Review Board approvals Title 41 — Public Contracts, Property Management required by Part 8 of the NASA Procurement Regulation...pursuant to paragraph (a) hereof, such amount or amounts Khali not Include any allowance for profit. In the event of any termination pursuant to paragraph (b)... | |
| 1980 - Broj stranica: 976
...required by Part 8 of the NASA Procurement Regulation in effect on the date of the execution of this contract, determine, on the basis of information available...event of any termination pursuant to paragraph (a) or (bXi) hereof, such amount or amounts shall not include any allowance for fee. In the event of any... | |
| 1983 - Broj stranica: 1104
...execution of this contract, determine, on the basis of information available to him, the amount, if iny, due to the Contractor by reason of the termination,...event of any termination pursuant to paragraph (a) or (bX>) hereof, such amount or amounts shall not include any allowance for fee. In the event of any... | |
| 1988 - Broj stranica: 1016
...Settlement Review Board approvals required by Subpart 1849.1 of the NASA FAR Supplement in effect as of the date of execution of this Letter Contract,...the event of any termination pursuant to paragraph i in hereof, such amount or amounts may include a reasonable allowance for profit, but only on work... | |
| |