" Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change: Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may... "
The Code of Federal Regulations of the United States of America - Stranica 375
1972
Potpun prikaz - O ovoj knjizi

Cases Decided in the United States Court of Claims ... with ..., Opseg 148

United States. Court of Claims, Audrey Bernhardt - 1962 - Broj stranica: 784
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the..."Disputes." However, nothing in this clause shall excuse the Con148 c. Os. Per Cariam tractor from proceeding with the contract as changed. * * * * * 12. DISPUTES...
Potpun prikaz - O ovoj knjizi

Code of Federal Regulations: Containing a Codification of Documents of ...

1969 - Broj stranica: 790
...cost or delivery schedule, or both, (2) in the amount of any fee to be paid to the Contractor, and (3) in such other provisions of the contract as may be...to any adjustment shall be a dispute concerning a question oí fact within the meaning of the clause oí this contract entitled "Disputes". However,...
Potpun prikaz - O ovoj knjizi

The Code of Federal Regulations of the United States of America

1972 - Broj stranica: 914
...cost or delivery schedule, or both, (2) In the amount of any fee to be paid to the Contractor, and (3) In such other provisions of the contract as may be...to any adjustment shall be a dispute concerning a question of fact within the meaning of the clause of thla contract entitled "Disputes". However, nothing...
Potpun prikaz - O ovoj knjizi

Code of Federal Regulations: Containing a Codification of Documents of ...

1972 - Broj stranica: 914
...cost or delivery schedule, or both, (2) in the amount of any fee to be paid to the Contractor, and (3) in such other provisions of the contract as may be...contract. Failure to agree to any adjustment shall bea dispute concerning a question of fact within the meaning of the clause of this contract entitled...
Potpun prikaz - O ovoj knjizi

Code of Federal Regulations: Containing a Codification of Documents of ...

1980 - Broj stranica: 976
...Any claim by the Contractor for adjustment under this clause must be asserted within sixty (6O) days from the date of receipt by the Contractor of the..."Disputes." However, nothing In this clause shall excuse th« Contractor from proceeding with the contract as changed. (End of clause) NASA PROCUREMENT REGULATION...
Potpun prikaz - O ovoj knjizi

The Code of Federal Regulations of the United States of America

1984 - Broj stranica: 720
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the...clause of this contract entitled "Disputes." However, except as provided in paragraph (c>, below, nothing In this clause shall excuse the Contractor from...
Potpun prikaz - O ovoj knjizi

The Code of Federal Regulations of the United States of America

1982 - Broj stranica: 532
...Contractor for adjustment under this clause must be asserted within thirty (30) days from the date or receipt by the Contractor of the notification of change;...to any adjustment shall be a dispute concerning a question of fact within, the meaning of the "Disputes" clause of this contract. However, nothing in...
Potpun prikaz - O ovoj knjizi

Code of Federal Regulations: Containing a Codification of Documents of ...

1979 - Broj stranica: 520
...Contractor for adjustment under this clause must be asserted within thirty (30) days from the date or receipt by the Contractor of the notification of change;...to any adjustment shall be a dispute concerning a question of fact within, the meaning of the "Disputes" clause of this contract. However, nothing in...
Potpun prikaz - O ovoj knjizi

Code of Federal Regulations: Containing a Codification of Documents of ...

1978 - Broj stranica: 944
...Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor of the...contract. Failure to agree to any adjustment shall be • dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract....
Potpun prikaz - O ovoj knjizi

The Code of Federal Regulations of the United States of America

1977 - Broj stranica: 944
...by the Contractor of the notification of change: Prodded, however, That the Contracting Officer, It he decides that the facts justify such action, may...clause of this contract entitled "Disputes." However, except as provided In paragraph (c), below, nothing In this clause shall excuse the Contractor from...
Potpun prikaz - O ovoj knjizi